Timeline for Implementation

 December 2014/January 2015
    Notification mailed to Existing 97-03-DWQ
      dischargers to recertify under new General Permit
    Notification includes the WDID and a Secret Code
      Number
    Dischargers begin the recertification process

 January – April 2015
    SMARTS development of new permit functions

 April – June 2015
    SMARTS beta testing
    External users can test and submit feedback

       Timeline for Implementation

 July 1, 2015
    July 1st effective date of Permit and recertification
      process complete
    SMARTS system ready to accept new applications
      and reports: NOI, NEC, NONA, monitoring data
    WDID numbers not recertified are “Expired”

 July – October 2015
    Water Boards sends Notices of Non-Compliance

 July 15, 2016

    1st Annual Report due via SMARTS