Industrial General Permit Fact Sheet

    certified and submitted, a Discharger will need to develop an Action Plan for this
    new Level 2 NAL exceedance. This General Permit defines new Level 2 NAL
    exceedances as an exceedance for a new parameter in any drainage area at the
    facility, or an exceedance for the same parameter being addressed in an existing
    Action Plan, but where the exceedance occurred in a different drainage area than
    identified in the existing Action Plan.

b. Level 2 ERA Technical Reports

    The Level 2 ERA Technical Report contains three different options that require a
    Discharger to submit demonstrations showing the cause of the NAL
    exceedance(s). This General Permit requires a Discharger to appoint a QISP to
    prepare the Level 2 ERA Technical Reports. The State Water Board
    acknowledges that there may be cases where a combination of the
    demonstrations may be appropriate; therefore a Discharger may combine any of
    the following three demonstration options in their Level 2 ERA Technical Report
    when appropriate. A Discharger is only required to annually update its Level 2
    ERA Technical Report when necessary as defined in Section XII.D.3.c of this
    General Permit, and is not required to annually re-certify and re-submit the entire
    Level 2 ERA Technical Report. If there are no changes prompting an update of
    the Level 2 ERA Technical Report, as specified in Section XII.D.3.c of this
    General Permit, the Discharger will provide this certification in the Annual Report
    that there have been no changes warranting re-submittal of the Level 2 ERA
    Technical Report.

    i. Industrial Activity BMPs Demonstration

         The Industrial Activity BMPs Demonstration is for the following:

          Dischargers who decided to implement additional BMPs that are expected
             to eliminate future NAL exceedance(s) and that have been implemented in
             order to achieve compliance with the technology-based effluent limitations
             of this General Permit, and

          Dischargers who decided to implement additional BMPs that may not
             eliminate future NAL exceedance(s) and that have been implemented in
             order to achieve compliance with the technology-based effluent limitations
             of this General Permit.

         When preparing the Industrial Activity BMPs Demonstration, the QISP shall
         identify and evaluate all individual pollutant source(s) associated with
         industrial activity that are or may be related to an NAL exceedance and all
         designed, information on the drainage areas associated with the Level 2 NAL
         exceedances, and installed BMPs that are implemented to reduce or prevent
         pollutants in industrial storm water discharges in compliance with this General
         Permit.