Industrial General Permit Fact Sheet
FIGURE 3: Compliance Determination Flowchart

2. Visual Observations

    There are two major changes to the visual observation requirements in this General
    Permit compared to the previous permit, which include:

    a. Monthly Visual Observations

         The previous permit required separate quarterly visual observations for
         unauthorized and authorized non-storm water discharges. It did not require
         periodic visual observations of the facility to determine whether all potential
         pollutant sources were being adequately controlled with BMPs. Prior drafts of
         this General Permit proposed the addition of pre-storm inspections. This was
         met with great resistance by Dischargers because of the complexity and burden
         of determining when a QSE would occur. Many of these Dischargers
         recommended that monthly BMP and non-storm water discharge visual
         observations should replace the proposed pre-storm inspections. This General
         Permit merges all visual observations into a single monthly visual observation.

    b. Sampling Event Visual Observations

Order 2014-0057-DWQ  45